🚧Construction Updates🚧

Current Projects

Road Renewal & Construction Impacts
A number of resurfacing, maintenance, and preservation projects are scheduled across Ward 21 in the coming months. Some work will include nighttime construction between 10:00 p.m. and 7:00 a.m., which may result in temporary noise impacts for nearby residents.

We will continue to share updates as these projects progress and appreciate your patience during this work to improve our roads.

Bridge Rehabilitation

  • Rideau Valley Drive South from Roger Stevens Drive to Lockhead Road East will be closed starting on Monday, June 29th, until late September for work to rehabilitate a bridge in the south end of Kars Village

    • Temporary access for pedestrians and cyclists will remain during construction on the bridge

  • Third Line Road South from Prince of Wales Drive to Roger Stevens Drive will be closed from Monday, June 29th until mid-November for work to rehabilitate the Stevens Creek Bridge northwest of North Gower Village

Culvert Renewals

June

  • Dorack Drive (0.01 km south of Rideauvale Ave) - road closure from Tues, June 16th to Mon, June 22nd

  • Fourth Line Road (0.01 km north of Century Rd W) - road closure from Weds, June 17th to Tues, June 23rd

  • Biltmore Crescent (0.21 km west of Munster Rd) - road closure from Mon, June 29th to Fri, July 10th

  • Munster Road (0.32 km south of Fallowfield Rd) - work starting on June 24th

  • Coldstream Drive (0.01 km east of Munster Rd) - road closure from Mon, July 6th to Weds, July 8th

  • William McEwen Drive (0.15 km north of Century Rd W) - road closure from Weds, June 29th to Tues, July 3rd

July

  • Fallowfield Road (0.02 km east of Munster Rd) - work starting on July 2nd

  • Roger Stevens Drive (0.14 km west of McKenna Rd) - work starting on July 6th

  • Fourth Line Road (0.06 km south of Callendor Rd) twin culvert renewal - starting on July 15th, with a road closure required for approximately 2 weeks

  • Fourth Line Road (0.15 km north of Dilworth Rd) - starting on July 15th, with a road closure required for approximately 2 weeks

August

  • Stratton Drive (0.01 km west of Third Line Rd) - starting on August 13th, with a road closure required for approximately 1 week

  • 2nd Line Road South (0.10 km north of Roger Stevens Dr) - starting on August 4th, with a road closure required for approximately 2 weeks

Road Renewal Projects

  • Bankfield Road, from Kilreen Lane to 370 metres west of Prince of Wales Drive

    • Work expected to start the week of July 6th

  • Black’s Side Road, from Fernbank Road to Ridingview Crescent

    • Work expected to start the week of August 31st

  • Brophy Drive, from Eagleson Road to Fourth Line Road

    • Work expected to start the week of August 4th

  • Community Way, from Fourth Line Road to Relin Way

    • Work expected to start the week of July 6th

  • Doctor Leach Drive, residential, from Beaverwood Road to Potter Drive (Tentative start date in mid-July)

  • Fallowfield Road, from Munster Road to Dwyer Hill Road

    • Work expected to start the week of August 10th

  • Farmstead Ridge, crack sealing, from Church Street to Church Street (Tentative start date in late August)

  • Fernbank Road, from Jinkinson Road to Munster Road

    • Work expected to start the week of September 8th

  • Fernbank Road, from 138 metres east of Shea Road to 385 metres east of Shea Road

  • Fourth Line Road, from Lockhead Road West to Shellstar Drive

    • Work expected to start the week of June 29th

  • Harbison Road, gravel road upgrade to hard asphalt surface, from Proven Line Road to McCordick Road (Tentative start date in mid-July)

  • Jinkinson Road, from Fernbank Road to 2.7 kilometres north of Fernbank Road

    • Work expected to start the week of August 24th

  • McBean Street, from Perth Street to Strachan Street

  • Phelan Road West, slurry seal, from Prince of Wales Drive to Ormond Road (Tentative start date in late July)

  • Rideau Valley Drive South, crack sealing, Dilworth Road to Roger Stevens Drive (Tentative start date in mid-August)

  • Shea Road, crack sealing, from Hemphill Street to Fernbank Road

* Dates/timing of the above works are to be determined and subject to change.


Other Construction Projects
➔ Hydro Work Supporting Dwyer Hill Training Facility Expansion
Hydro Ottawa is working on major electrical upgrades in Ward 21 to support the long-term expansion of the Department of National Defence’s Dwyer Hill Training Centre, a project scheduled to continue through 2034.

Phase 1: Hydro Pole and Equipment Installation on Dwyer Hill Road
--
Hydro Ottawa is installing new hydro poles and equipment along Dwyer Hill Road between Franktown Road and Jock Trail Road. This work will be carried out by Bradley Kelly Construction Ltd. and is expected to be completed by September 26, 2025.

Affected roads include Ashton Station Road, Dwyer Hill Road, and Purdy Road. Written notices will be delivered to affected households. If planned power outages are required for safety, additional notices will be issued in advance.

Phase 2: Transformer Installation and Infrastructure Upgrade on Garvin Road
--
Phase 2 has begun with the installation of a new 30 MVA transformer and the construction of a new building to house supporting electrical infrastructure at the Richmond South municipal transformer station on Garvin Road, just west of Huntley Road. This phase is expected to be completed by December 19, 2025.

Both projects will take place within Hydro Ottawa property and the City’s Road Right-of-Way, and all scheduling has been planned with customer convenience and safety in mind. Affected customers will receive door-to-door notices, including advance warnings for any planned outages.

You may notice increased construction activity in the area during the day. These infrastructure upgrades are essential to supporting the growing energy demands tied to national defence operations and the surrounding community.

➔ Pole Installation on Franktown Road
Hydro Ottawa is installing new hydro poles and equipment along Franktown Road between Conley Road and Munster Road. This work will be carried out by Bradley Kelly Construction Ltd. and is expected to be completed by February 2026. 


🗺 To explore citywide construction projects, use the City of Ottawa Interactive Construction Map.

Previous
Previous

Ottawa’s $1.9 Billion Capital Infrastructure Investment Season Begins

Next
Next

Newsletter - 22 May 2026