🚧Construction Updates🚧
Current Projects
Road Resurfacing & Construction Impacts
A number of resurfacing, maintenance, and preservation projects are scheduled across Ward 21 in the coming months. Some work will include nighttime construction between 10:00 p.m. and 7:00 a.m., which may result in temporary noise impacts for nearby residents.
We will continue to share updates as these projects progress and appreciate your patience during this work to improve our roads.
🛣 Resurfacing Projects
Bankfield Road
From 320m east of Hwy 416 overpass to Kilreen Lane
Start: Late July (work to tentatively start week of July 21) – Early September
Work Hours: Night work only (7:00 pm to 6:00 am)
Traffic: Road remains open; expect lane closuresMoodie Drive
From Fallowfield Road to 1300m north
Start: Work ongoingTwin Elm Road
From Brophy Road to 3890m north
Start: Late July (work to tentatively start week of July 28) - Late September
Work Hours: Daytime work (7:00 am to 10:00 pm)
Traffic: Road remains open; expect lane closuresBrophy Road
From 25m east of Fourth Line Road to 326m west of Hwy 416 overpass
Start: Late July (work to tentatively start week of July 21) - Late September
Work Hours: Night (6:00 pm to 7:00 am) and as needed during the day (7:00 am to 6:00 pm)
Traffic: Road remains open; expect lane closuresEagleson Road
From Old Richmond Road to Fallowfield Road
Status: Work ongoing until end of summerThird Line Road
From Phelan Road W to Prince of Wales Drive
Start: Early September (tentative start date of September 8)Third Line Road
From 115m south of Prince of Wales Drive to Roger Stevens Drive
Start: Late August (tentative start date of August 27)
🔧 Crack Sealing
Flewellyn Road
From Ashton Station Road to Munster Road
Start: Mid-July (tentative start date of July 22)Ashton Station Road
From Ormrod Road to Flewellyn Road
Start: Mid-July (tentative start date of July 22)Ormrod Road
From Ashton Station Road to Flewellyn Road
Start: Mid-July (tentative start date of July 22)
🛡 Pavement Preservation
Conley Road
From Franktown Road to Mansfield Road
Start: Mid-July (tentative start date of July 15)
🌉 Culvert Renewals
As part of a major infrastructure renewal project, the City of Ottawa will be replacing seven culverts across Ward 21 over the coming months. These upgrades are critical for maintaining safe and reliable roadways, particularly in areas prone to flooding or seasonal runoff.
Construction will take place at the following locations:
🛠 Scheduled Culvert Replacements
Brophy Drive
0.43 km east of Eagleson Road
📅 July 21–25Brophy Drive
0.58 km west of Fourth Line Road
📅 July 21–25Beaverwood Road
From Doctor Leach Drive to Scharfield Road
📅 July 21–31
➔ Full road closure for installation of site services (sanitary sewer, storm sewer, and watermain) for new building construction.Third Line Road
0.01 km south of Brophy Drive
📅 July 28 – August 1
➔ Third Line Road (Brophy Dr to Century Rd) may be closed from Monday, July 28 at 6:00 am until Friday, August 1 at 7:00 pm.Harnett Road
Approximately 0.29 km south of Mulholland Road
📅 August 11–15
➔ Full road closure between Mulholland Road and Paden Road for culvert replacement.
Detour: via Paden Road, Malakoff Road, and Gallagher Road.Second Line Road
0.10 km north of Roger Stevens Drive
📅 Planned for Fall 2025
➔ Details to follow closer to construction date.
🚧 Traffic impacts and detours may be in place during these dates. Please follow posted signage and allow extra travel time when passing through these areas.
🚧 Other Construction Projects
➔ Bridge Renewal Projects – Copeland and Garvin Roads
Two important bridge renewal projects are underway this summer in Ward 21 as part of the City’s Bundled Bridges Program. These upgrades will enhance the long-term safety and reliability of local road infrastructure and are scheduled to continue through to October 31, 2025, including final site restoration.
Project Details:
Copeland Road Bridge over the Jock River
🚧 Full road closure in effect now until September 10, 2025 (approximately 10 weeks)Garvin Road Bridge culvert over the Van Gaal West Main Municipal Drain
🚧 Full road closure from August 5 to September 19, 2025 (approximately 6 weeks)
What to Expect:
Detour plans have been developed to ensure safety and minimize disruption. Public notices are being delivered to residents and stakeholders in advance to support travel planning during the closures.
➔ Hydro Work Supporting Dwyer Hill Training Facility Expansion
Starting this summer, Hydro Ottawa will begin major electrical upgrades in Ward 21 to support the long-term expansion of the Department of National Defence’s Dwyer Hill Training Centre, a project scheduled to continue through 2034.
Phase 1: Hydro Pole and Equipment Installation on Dwyer Hill Road
--
Hydro Ottawa are installing new hydro poles and equipment along Dwyer Hill Road between Franktown Road and Jock Trail Road. This work will be carried out by Bradley Kelly Construction Ltd. and is expected to be completed by September 26, 2025.
Affected roads include Ashton Station Road, Dwyer Hill Road, and Purdy Road, with service impacts to approximately 49 customers. Written notices will be delivered to affected households. If planned power outages are required for safety, additional notices will be issued in advance.
Phase 2: Transformer Installation and Infrastructure Upgrade on Garvin Road
--
The next phase began on July 14, 2025, with the installation of a new 30 MVA transformer and the construction of a new building to house supporting electrical infrastructure at the Richmond South municipal transformer station on Garvin Road, just west of Huntley Road. This phase is expected to be completed by December 19, 2025.
Pile driving will occur for approximately three weeks during this period to install concrete foundations. Residents nearby may experience temporary noise and vibration disruptions, and Hydro Ottawa appreciates your patience and understanding as crews work to complete this work safely and efficiently.
Both projects will take place within Hydro Ottawa property and the City’s Road Right-of-Way, and all scheduling has been planned with customer convenience and safety in mind. Affected customers will receive door-to-door notices, including advance warnings for any planned outages.
You may notice increased construction activity in the area during the day. These infrastructure upgrades are essential to supporting the growing energy demands tied to national defence operations and the surrounding community.
➔ Road Closure: Franktown Road
Location: Franktown Road from Matilda Gate to Dwyer Hill Road
Dates: Monday, August 11 to Friday, August 15, 2025
Contractor: R.W. Tomlinson Ltd.
Road Closure Impact: Medium
Detour: No signed detour route (local traffic to follow posted signage)
Pre-Notification: Notice letters and portable variable message signs (PVMS) in place
As part of infrastructure work for the Eastern Ontario Campus project, R.W. Tomlinson Ltd. will be installing:
A new 300mm PVC watermain
A 250mm PVC sanitary sewer
A second 250mm PVC watermain
A communications ductbank crossing
Please plan alternate routes during the closure period and allow extra time for travel in the area.
🗺 To explore citywide construction projects, use the City of Ottawa Interactive Construction Map.