🚧Construction Updates🚧
Current Projects
Construction Update: Watermain Installation on Perth Street (Richmond)
I’m writing to inform residents that watermain installation work will be taking place across Perth Street (southwest of the roundabout) during the week of June 16th. To accommodate this work, flagging operations and daytime lane reductions will be required. Please note that all lanes will reopen in the evening, and the road surface will be temporarily reinstated with granular material at the end of each workday.
Temporary asphalt paving is scheduled for the week of June 23rd, with final asphalt reinstatement planned for later in July or August.
Road Resurfacing & Construction Impacts
A number of resurfacing, maintenance, and preservation projects are scheduled across Ward 21 in the coming months. Some work will include nighttime construction between 10:00 p.m. and 7:00 a.m., which may result in temporary noise impacts for nearby residents.
We will continue to share updates as these projects progress and appreciate your patience during this work to improve our roads.
🛣 Resurfacing Projects
Bankfield Road
From 320m east of Hwy 416 overpass to Kilreen Lane
Start: Late July – Early SeptemberMoodie Drive
From Fallowfield Road to 1300m north
Start: Early July - Late SeptemberTwin Elm Road
From Brophy Road to 3890m north
Start: Late July - Late SeptemberBrophy Road
From 25m east of Fourth Line Road to 326m west of Hwy 416 overpass
Start: Late July - Late SeptemberEagleson Road
From Old Richmond Road to Fallowfield Road
Status: Work ongoing until end of summer (*Road closure will commence on or around July 2nd*)Third Line Road
From Phelan Road W to Prince of Wales Drive
Start: Early SeptemberThird Line Road
From 115m south of Prince of Wales Drive to Roger Stevens Drive
Start: Late August
🔧 Crack Sealing (Starting September)
Flewellyn Road – From Ashton Station Road to Munster Road
Ashton Station Road – From Ormrod Road to Flewellyn Road
Ormrod Road – From Ashton Station Road to Flewellyn Road
🚜 Gravel Road Upgrades
Phelan Road West
From Prince of Wales Drive to Ormond Road
Status: Work ongoing
🛡 Pavement Preservation
Conley Road
From Franktown Road to Mansfield Road
Start: Mid-July
🌉 Culvert Renewals
As part of a major infrastructure renewal project, the City of Ottawa will be replacing seven culverts across Ward 21 over the coming months. These upgrades are critical for maintaining safe and reliable roadways, particularly in areas prone to flooding or seasonal runoff.
Construction will take place at the following locations:
🛠 Scheduled Culvert Replacements
Bankfield Road
0.64 km west of Prince of Wales Drive
📅 June 23–27William McEwen Drive
0.01 km north of Brophy Drive
📅 July 14–18Brophy Drive
0.43 km east of Eagleson Road
📅 July 21–25Brophy Drive
0.58 km west of Fourth Line Road
📅 July 21–25Third Line Road
0.01 km south of Brophy Drive
📅 July 28 – August 1Second Line Road
0.10 km north of Roger Stevens Drive
📅 Planned for Fall 2025
🚧 Traffic impacts and detours may be in place during these dates. Please follow posted signage and allow extra travel time when passing through these areas.
🚧 Other Construction Projects
No new updates to report at this time.
🗺 To explore citywide construction projects, use the City of Ottawa Interactive Construction Map.