🚧Construction Updates🚧

Current Projects

Construction Update: Watermain Installation on Perth Street (Richmond)

I’m writing to inform residents that watermain installation work will be taking place across Perth Street (southwest of the roundabout) during the week of June 16th. To accommodate this work, flagging operations and daytime lane reductions will be required. Please note that all lanes will reopen in the evening, and the road surface will be temporarily reinstated with granular material at the end of each workday.

Temporary asphalt paving is scheduled for the week of June 23rd, with final asphalt reinstatement planned for later in July or August.

Road Resurfacing & Construction Impacts
A number of resurfacing, maintenance, and preservation projects are scheduled across Ward 21 in the coming months. Some work will include nighttime construction between 10:00 p.m. and 7:00 a.m., which may result in temporary noise impacts for nearby residents.

We will continue to share updates as these projects progress and appreciate your patience during this work to improve our roads.

🛣 Resurfacing Projects

  • Bankfield Road
    From 320m east of Hwy 416 overpass to Kilreen Lane
    Start: Late July – Early September

  • Moodie Drive
    From Fallowfield Road to 1300m north
    Start: Early July - Late September

  • Twin Elm Road
    From Brophy Road to 3890m north
    Start: Late July - Late September

  • Brophy Road
    From 25m east of Fourth Line Road to 326m west of Hwy 416 overpass
    Start: Late July - Late September

  • Eagleson Road
    From Old Richmond Road to Fallowfield Road
    Status: Work ongoing until end of summer (*Road closure will commence on or around July 2nd*)

  • Third Line Road
    From Phelan Road W to Prince of Wales Drive
    Start: Early September

  • Third Line Road
    From 115m south of Prince of Wales Drive to Roger Stevens Drive
    Start: Late August

🔧 Crack Sealing (Starting September)

  • Flewellyn Road – From Ashton Station Road to Munster Road

  • Ashton Station Road – From Ormrod Road to Flewellyn Road

  • Ormrod Road – From Ashton Station Road to Flewellyn Road

🚜 Gravel Road Upgrades

  • Phelan Road West
    From Prince of Wales Drive to Ormond Road
    Status: Work ongoing

🛡 Pavement Preservation

  • Conley Road
    From Franktown Road to Mansfield Road
    Start: Mid-July


🌉 Culvert Renewals

As part of a major infrastructure renewal project, the City of Ottawa will be replacing seven culverts across Ward 21 over the coming months. These upgrades are critical for maintaining safe and reliable roadways, particularly in areas prone to flooding or seasonal runoff.

Construction will take place at the following locations:

🛠 Scheduled Culvert Replacements

  • Bankfield Road
    0.64 km west of Prince of Wales Drive
    📅 June 23–27

  • William McEwen Drive
    0.01 km north of Brophy Drive
    📅 July 14–18

  • Brophy Drive
    0.43 km east of Eagleson Road
    📅 July 21–25

  • Brophy Drive
    0.58 km west of Fourth Line Road
    📅 July 21–25

  • Third Line Road
    0.01 km south of Brophy Drive
    📅 July 28 – August 1

  • Second Line Road
    0.10 km north of Roger Stevens Drive
    📅 Planned for Fall 2025

🚧 Traffic impacts and detours may be in place during these dates. Please follow posted signage and allow extra travel time when passing through these areas.


🚧 Other Construction Projects

  • No new updates to report at this time.

🗺 To explore citywide construction projects, use the City of Ottawa Interactive Construction Map.

Previous
Previous

Newsletter - 29 May 2025

Next
Next

Newsletter - 15 May 2025